Q221. The Japanese Quality Control (QC) Circle movement motivated its participants in many ways. Which of the following represents the most important motivation for the QC circle participants?

A. strengthening of relationships between co-workers

B. recognition among co-workers

C. self-improvement

D. improving the performance of the company

E. financial incentives

Answer: D


Q222. Which is the document that presents a hierarchical project organization?

A. WBS

B. CPI

C. OBS

D. BOM

Answer: C


Q223. Which process group defines the course of action required to attain the objectives that the project was undertaken to achieve?

A. Initiating

B. Executing

C. Planning

D. Monitoring and Controlling

Answer: C


Q224. What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

A. Decomposition

B. Benchmarking

C. Inspection

D. Checklist analysis

Answer: C


Q225. A work authorization system can be used to:

A. Manage who does each activity.

B. Manage when and in what sequence work is done.

C. Manage when each activity is done.

D. Manage who does each activity and when it is done.

Answer: B


Q226. In which tool and technique is it possible to find a correlation between dependent and independent variables?

A. Fishbone diagram

B. Control chart

C. Run chart

D. Scatter diagram

Answer: D


Q227. What is an output of Control Scope?

A. Accepted deliverables

B. Work performance measurements

C. Requirements documentation

D. Work performance information

Answer: B


Q228. Linear programming is an example of what type of project selection criteria?

A. Constrained optimization

B. Comparative approach

C. Benefit measurement

D. Impact analysis

Answer: A


Q229. Which of the following is an input to Develop Human Resource Plan?

A. Team performance assessment

B. Roles and responsibilities

C. Staffing management plan

D. Enterprise environmental factors

Answer: D


Q230. The project management processes presented in the PMBOK Guide should:

A. Always be applied uniformly

B. Be selected as appropriate by the sponsor

C. Be selected as appropriate by the project team

D. Be applied based on ISO guidelines.

Answer: C