Q171. Management styles associated with production environments, such as assembly lines commonly include:

A.

C. Using the previous project's WBS as a template

D. Reusing the previous project's cost-benefit analysis as justification for this project

Answer: C


Q173. Which of the following equations is used to calculate cost variance?

A. EV-AC

B. AC-EV

C. AC+EV

D. AC/EV

Answer: A


Q174. What is an objective of the Developing Project Team Process?

A. Feelings of trust and improved cohesiveness

B. Ground rules for interaction

C. Enhanced resource availability

D. Functional managers become more involved.

Answer: A


Q175. Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A. Project Integration Management

B. Project Communications Management

C. Project Information Management System (PIMS)

D. Project Scope Management

Answer: B


Q176. You are about to begin negotiations with people from another country. Which of the following should provide guidance on what business practices are allowed and not allowed?

A. The company code of conduct

B. The project charter

C. The scope management plan

D. The negotiation plan

Answer: A


Q177. A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

A. Parametric

B. Bottom up.

C. Budget

D. Top down.

E. Definitive.

Answer: C


Q178. Which tool and technique uses a statistical relationship between historical data and other variables to calculate estimates?

A. Analogous estimating

B. Three-point estimates

C. Parametric estimating

D. Bottom-up estimating

Answer: C


Q179. Communication always makes use of.

A. words

B. All of the other alternatives apply.

C. language

D. gestures

E. symbols

Answer: B


Q180. Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

A. Scope plan

B. Product scope

C. Scope management plan

D. Scope baseline

Answer: D