Your success in PMI CAPM is our sole target and we develop all our CAPM braindumps in a way that facilitates the attainment of this target. Not only is our CAPM study material the best you can find, it is also the most detailed and the most updated. CAPM Practice Exams for PMI CAPM are written to the highest standards of technical accuracy.

Also have CAPM free dumps questions for you:

NEW QUESTION 1

Funding limit reconciliation is a tool and technique used in which process?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Control Budget

Answer: B

NEW QUESTION 2

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

  • A. Monitoring and Controlling
  • B. Initiating
  • C. Planning
  • D. Executing

Answer: A

NEW QUESTION 3

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

  • A. Limited
  • B. Low to moderate
  • C. Moderate to high
  • D. High to almost total

Answer: C

NEW QUESTION 4

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

  • A. Checksheets
  • B. Histograms
  • C. Flowcharts
  • D. Control charts

Answer: C

NEW QUESTION 5

Risk exists the moment that a project is:

  • A. planned.
  • B. conceived.
  • C. chartered.
  • D. execute

Answer: B

NEW QUESTION 6

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

  • A. Requirements documentation
  • B. Requirements traceability matrix
  • C. Project management plan updates
  • D. Project documents updates

Answer: B

NEW QUESTION 7

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

  • A. Estimate Costs
  • B. Control Costs
  • C. Plan Cost Management
  • D. Determine Budget

Answer: D

NEW QUESTION 8

A technique used to determine the cause and degree of difference between baseline and actual performance is:

  • A. Product analysis.
  • B. Variance analysis.
  • C. Document analysis,
  • D. Decompositio

Answer: B

NEW QUESTION 9

An output of the Perform Integrated Change Control process is:

  • A. Deliverables.
  • B. Validated changes.
  • C. The change log.
  • D. The requirements traceability matri

Answer: C

NEW QUESTION 10

Which stakeholder approves a project's result?

  • A. Customer
  • B. Sponsor
  • C. Seller
  • D. Functional manager

Answer: A

NEW QUESTION 11

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

  • A. Continuous
  • B. Discrete
  • C. Regulated
  • D. Arbitrary

Answer: A

NEW QUESTION 12

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

  • A. Resource breakdown structure
  • B. Staffing management plan
  • C. Project organizational chart
  • D. Scope management plan

Answer: B

NEW QUESTION 13

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  • A. Available organizational assets
  • B. Project staff assignments
  • C. Interpersonal skills
  • D. Enterprise environmental factors

Answer: A

NEW QUESTION 14

An intentional activity to modify a nonconforming product or product component is called:

  • A. defect repair
  • B. work repair
  • C. corrective action
  • D. preventive action

Answer: A

NEW QUESTION 15

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

  • A. Bottom-up
  • B. Parametric
  • C. Analogous
  • D. Three-point

Answer: C

NEW QUESTION 16

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

  • A. Strong
  • B. Weak
  • C. Managed
  • D. Balanced

Answer: D

NEW QUESTION 17

Which of the following involves making information available to project stakeholders in a timely manner?

  • A. Plan Communications
  • B. Performance reporting
  • C. Project status reports
  • D. Distribute Information

Answer: D

NEW QUESTION 18

Which of the following is an input to Control Scope?

  • A. Project schedule
  • B. Organizational process assets updates
  • C. Project document updates
  • D. Work performance information

Answer: D

NEW QUESTION 19

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

  • A. Scope baseline
  • B. Organizational process assets
  • C. Enterprise environmental factors
  • D. Risk register

Answer: C

NEW QUESTION 20

The Human Resource Management processes are:

  • A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
  • B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
  • C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
  • D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Tea

Answer: A

NEW QUESTION 21

Tools and techniques used for Plan Communications include the communication:

  • A. requirements analysis, communication technology, communication models, and communication methods.
  • B. methods, stakeholder register, communication technology, and communication models.
  • C. requirements, communication technology, communication requirements analysis, and communication methods.
  • D. management plan, communication technology, communication models, and communication requirements analysi

Answer: A

NEW QUESTION 22

Which of the following is TRUE about most project life cycles?

  • A. Staffing level is highest at the start.
  • B. The stakeholders' influence is highest at the start.
  • C. The level of uncertainty is lowest at the start.
  • D. The cost of changes is highest at the star

Answer: B

NEW QUESTION 23

What are the Project Procurement Management processes?

  • A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
  • B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
  • C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
  • D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Answer: C

NEW QUESTION 24

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

  • A. 1.33
  • B. 2
  • C. 0.75
  • D. 0.5

Answer: A

NEW QUESTION 25

In which process is a project manager identified and given the authority to apply resources to project activities?

  • A. Acquire Project Team
  • B. Develop Project Management Plan
  • C. Manage Project Execution
  • D. Develop Project Charter

Answer: D