Passleader offers free demo for CAPM exam. "Certified Associate in Project Management (PMI-100)", also known as CAPM exam, is a PMI Certification. This set of posts, Passing the PMI CAPM exam, will help you answer those questions. The CAPM Questions & Answers covers all the knowledge points of the real exam. 100% real PMI CAPM exams and revised by experts!
Online CAPM free questions and answers of New Version:
NEW QUESTION 1
Which of the following is a tool and technique used in the Develop Schedule process?
- A. Three-point estimates
- B. Resource leveling
- C. Precedence diagramming method
- D. Bottom-up estimating
Answer: B
NEW QUESTION 2
What is the total float of the critical path?
- A. Can be any number
- B. Zero or positive
- C. Zero or negative
- D. Depends on the calendar
Answer: C
NEW QUESTION 3
Which action is included in the Control Costs process?
- A. Identify how the project costs will be planned, structured, and controlled
- B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
- C. Develop an approximation of the monetary resources needed to complete project activities
- D. Monitor cost performance to isolate and understand variances from the approved cost baseline
Answer: D
NEW QUESTION 4
An input to the Collect Requirements process is the:
- A. stakeholder register.
- B. project management plan.
- C. project scope statement.
- D. requirements management pla
Answer: A
NEW QUESTION 5
In project management, a temporary project can be:
- A. Completed without planning
- B. A routine business process
- C. Long in duration
- D. Ongoing to produce goods
Answer: C
NEW QUESTION 6
Which is an output of the Collect Requirements process?
- A. Requirements traceability matrix
- B. Project scope statement
- C. WBS dictionary
- D. Work performance measurements
Answer: A
NEW QUESTION 7
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
- A. event.
- B. response,
- C. perception.
- D. impac
Answer: A
NEW QUESTION 8
Organizations perceive risks as:
- A. events that will inevitably impact project and organizational objectives.
- B. the effect of uncertainty on their project and organizational objectives.
- C. events which could have a negative impact on project and organizational objectives.
- D. the negative impact of undesired events on their project and organizational objective
Answer: B
NEW QUESTION 9
Which enterprise environmental factors may influence Plan Schedule Management?
- A. Cultural views regarding time schedules and professional and ethical behaviors
- B. Historical information and change control procedures
- C. Risk control procedures and the probability and impact matrix
- D. Resource availability and organizational culture and structure
Answer: D
NEW QUESTION 10
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
- A. Earned value management.
- B. Enterprise environmental factors.
- C. Organizational process assets.
- D. Work performance informatio
Answer: D
NEW QUESTION 11
Which of the following techniques is used during Control Scope?
- A. Cost-benefit analysis
- B. Variance analysis
- C. Reserve analysis
- D. Stakeholder analysis
Answer: B
NEW QUESTION 12
Project Scope Management is primarily concerned with:
- A. Developing a detailed description of the project and product.
- B. Determining how requirements will be analyzed, documented, and managed.
- C. Defining and controlling what is and is not included in the project.
- D. Formalizing acceptance of the completed project deliverable
Answer: C
NEW QUESTION 13
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
- A. Initiating
- B. Planning
- C. Executing
- D. Closing
Answer: C
NEW QUESTION 14
An input to Close Project or Phase is:
- A. Accepted deliverables,
- B. Final products or services,
- C. Document updates,
- D. Work performance information.
Answer: A
NEW QUESTION 15
An output of the Direct and Manage Project Work process is:
- A. Deliverables.
- B. Activity lists.
- C. A work breakdown structure.
- D. A scope statemen
Answer: A
NEW QUESTION 16
Quality metrics are an output of which process?
- A. Plan Quality
- B. Perform Quality Control
- C. Perform Quality Assurance
- D. Perform Qualitative Risk Analysis
Answer: A
NEW QUESTION 17
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
- A. Organizational breakdown structure (OBS)
- B. Work performance information
- C. Work package
- D. Work breakdown structure (WBS)
Answer: D
NEW QUESTION 18
When sequencing activities, what does the common acronym FF stand for?
- A. Fixed Fee
- B. Free Float
- C. Fixed Finish
- D. Finish-to-Finish
Answer: D
NEW QUESTION 19
Plan Schedule Management is a process in which Knowledge Area?
- A. Project Scope Management
- B. Project Human Resource Management
- C. Project Integration Management
- D. Project Time Management
Answer: D
NEW QUESTION 20
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
- A. Keep satisfied
- B. Keep informed
- C. Manage closely
- D. Monitor
Answer: A
NEW QUESTION 21
The Verify Scope process is primarily concerned with:
- A. formalizing acceptance of the completed project deliverables.
- B. accuracy of the work deliverables.
- C. formalizing approval of the scope statement.
- D. accuracy of the work breakdown structure (WBS).
Answer: A
NEW QUESTION 22
The procurement process that documents agreements and related documentation for future reference is known as:
- A. Plan Procurements.
- B. Control Procurements.
- C. Close Procurements.
- D. Conduct Procurement
Answer: C
NEW QUESTION 23
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
- A. adaptive
- B. reflexive
- C. predictive
- D. iterative
Answer: A
NEW QUESTION 24
What is the most accurate rough order of magnitude (ROM)?
- A. In the Initiation phase, the estimate is in the range of +/- 50%.
- B. In the Planning phase, the estimate is in the range of +/- 50%.
- C. In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
- D. In the Closing phase, the estimate is in the range of +/- 15%.
Answer: A
NEW QUESTION 25
Testing falls into which of the following categories of cost of quality?
- A. Internal failure costs
- B. Prevention costs
- C. Appraisal costs
- D. External failure costs
Answer: C