Master the OG0-092 Braindumps content and be ready for exam day success quickly with this OG0-092 Dumps Questions. We guarantee it!We make it a reality and give you real OG0-092 Exam Dumps in our The Open Group OG0-092 braindumps. Latest 100% VALID OG0-092 Braindumps at below page. You can use our The Open Group OG0-092 braindumps and pass your exam.

The Open Group OG0-092 Free Dumps Questions Online, Read and Test Now.

NEW QUESTION 1
Scenario:
Please read this scenario prior to answering the Question
You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems. Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored Content Metamode
  • B. As the environment is process-centric this will enable them to model the manufacturing processes and store information to support regulatory complianc
  • C. It also includes views useful for managing the consolidation of applications into a single data center.
  • D. You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamode
  • E. This is suitable as this is a significant IT change that will impact its operational model
  • F. This will ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.
  • G. You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamode
  • H. This would allow modeling of the target milestones they want to achieve with this consolidation of application to a single data cente
  • I. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.
  • J. You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamode
  • K. This would allow modeling of the location of IT assets and ensure regulatory compliance for the manufacturing proces
  • L. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.

Answer: A

NEW QUESTION 2
Magic Wand Corporation manufactures a range of equipment used by magician worldwide. The global popularity of a series of children’s books describing the formative years of a budding wizard and his various escapades at wizard school has driven unprecedented sales growth in the magical equipment market.
The current IT systems at Magic Wand are struggling to cope with the high volumes in this growth market. The CIO wants to persuade the board of Magic Wand Corporation to make a greater investment in the IT systems to cope with the new higher transaction volumes. On of the key components the CIOs wants to include when he approaches the board is a description of the current problems and how they may be addressed from an architectural point of view.
As the High Architect of Magic Wand Corporation, the CIO has delegated the task of
creating a vision for the future Architecture to you.
Which of the following answers best describes how TOGAF recommends delivering an Architecture Vision for the CIO?

  • A. Firstly, I ensure there is a Request for Architecture Work from the CI
  • B. Then I ensure that there is recognition for the architecture vision project by following any project management and programmed management frameworks used within the organizatio
  • C. I would identify the key stakeholders and engage with them to understand and document their concerns and high-level requirement
  • D. This would result in a stakeholder map used to support other deliverables such as the Architecture Vision, a Communications plan and a Statement of Architecture Wor
  • E. I would then identify the business goals and strategic drivers of the organization and define any enterprise or project specific constraints such as time and resource
  • F. I would then define the business capabilities of the organization needed to fulfill those business goals and drivers and their readiness for chang
  • G. Once complete, I would define the scope, confirm the architecture and business principles and develop the Architecture Visio
  • H. Following this, I would define the business case for the architecture project, assess the business risks and produce a risk mitigation pla
  • I. I would then define a plan of enterprise architecture work to meet the scope in the desired time line and the resources required and secure the support of stakeholders.
  • J. I would start by ensuring there is a Request for Architecture Work from the sponsor (the CIO). I would then create a project to define and deliver the architecture vision and the necessary output
  • K. The outputs include an approved Statement of Architecture Work, refined statements of Businesses Principles, Business Goals and Business Drivers, Architecture Principles, a Capability Assessment, a Tailored Architecture Framework, an Architecture vision, a Communications pla
  • L. The Statement of Architecture Work needs to be clear on the scope of architectural work, the resources needed to complete the work and amount of time it would take to complete the work assuming the scope of architectural work is agreed and that all the resources required are availabl
  • M. The final step would be to agree the Statement of Architectural Work with stakeholders confirming the scope, schedule and confirming the availability of the necessary resources.
  • N. I would start by establishing the architecture project and follow the appropriate project management metho
  • O. I would identify stakeholders their concerns and business requirements then confirm and elaborate the business goals, business drivers and constraint
  • P. I would then evaluate the business capabilities and readiness for business transformation and define the scop
  • Q. I would then develop the architecture vision, define the target architecture value proposition, KPIs and identify and mitigate all risks associated with the transformation effor
  • R. Finally, I would develop an Enterprise Architecture Plan and Statement of Work and secure approval from the relevant stakeholders.
  • S. I would approach this by defining and establishing the architecture team and governanc
  • T. This would be followed by agreeing and establishing the architecture principle
  • U. I would select and customize an architecture framework changing any terminology and selecting the right phases and customizing the structure of content and outputs from the chosen metho
  • V. Finally I would select and implement and architecture tool
  • W. The outputs from this work would include an Organization Model for EnterpriseArchitecture, a Tailored Architecture Framework including method and content, the Architecture Principles, an initial architecture repository, restatement or references to business principles, business goals and business driver, a request for architecture work and the governance framework.

Answer: A

NEW QUESTION 3
ARTI Dimensioning is a multinational that operates production facilities in 29 countries and sells its products in over 120 countries.
A consultancy firm has recommended a realignment that will enhance sharing of product information across business units. The implementation of this strategic realignment will require the development of integrated customer information systems and product information systems.
ARTI has a mature enterprise architecture practice and uses TOGAF 9 for the basis of the ARTI Architecture Framework (method and deliverables). The CIO is sponsoring an architecture development program that is going to start. The CIO is concerned about a potential disruptive result to the business of this activity and before proceeding with the architecture development he asked to evaluate the impacts on the company business.
Refer to the scenario above You are the Lead Architect and you have been asked to recommend an approach to address the concerns raised. Based on TOGAF 9 recommend which of the following is the best answer.
Choose one of the following answers.

  • A. Risk Aversion Assessment should be conducted during the Implementation Governance phase to determine the degree of risk aversion of the proposed business transformatio
  • B. After sharing the residual level of risk with the company chairman and the residual risk is not accepted, a set of parallel systems will be implemented to mitigate the risks.
  • C. Your recommendation is to use risk management techniques to assess the risks associated with the proposed business transformation and ensure the existence of business continuity plan
  • D. During the Implementation Governance phase you conduct a residual risk assessment to manage risks that cannot be mitigated.
  • E. During the Architecture Vision phase a risk assessment is conducted to mitigate initial risks and address those in the Architecture Contract signed in the Implementation Governance phase.
  • F. Your proposal is to utilize a risk management framework during the Implementation Governance phase to verify the risks associated with the proposed transformation of the busines
  • G. You then share with the concerned stakeholders the residual level on risk beforethe Architecture Contracts are released.

Answer: B

NEW QUESTION 4
Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO. Based on TOGAF 9, which of the following is the best answer?

  • A. In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful introduction of the architecture into the organizatio
  • B. There should then be an assessment of each factor on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fi
  • C. Thesefactors can then be used to assess the initial risks associated with the proposed architecture.
  • D. In Phase A the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deploymen
  • E. The matrix should include a list of factors to be considered, their descriptions, and constraints that should be taken into accoun
  • F. These factors can then used to assess the initial risks associated with the proposed architecture.
  • G. In Phase A, the team should use the Business Transformation Readiness Assessment technique to identify the factors that will influence the successful introduction of the architecture into the organizatio
  • H. The assessment should include determining the readiness rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fi
  • I. These factors can then used to assess the initial risks associated with the proposed architecture.
  • J. In Phase A, the team should conduct a Business Scenario to identify the stakeholders' concerns and the resulting retirement
  • K. Once the retirements have been identified, they can be assessed in terms of their risk
  • L. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigate
  • M. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board.

Answer: C

NEW QUESTION 5
Scenario:
Please read this scenario prior to answering the question
You are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies.
Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture
Board approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.
Refer to the Scenario
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

  • A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk managemen
  • B. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definitio
  • C. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • D. You create an Architecture Contract to manage and govern the implementation and migration process at each locatio
  • E. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organizatio
  • F. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • G. You create an Architecture Contract to manage and govern the implementation and migration proces
  • H. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contrac
  • I. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • J. You use the issued Architecture Contracts to manage the architecture governance processes for the project across the location
  • K. You deploy monitoring tools to assess the performance of the completed blade assembly at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the abilityto customize the process to meet their local need
  • L. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.

Answer: A

NEW QUESTION 6
Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Chief Enterprise Architect within a leading North American information technology services company. The company has a number of service portfolios including infrastructure, applications, business process outsourcing, accounting, and financial services.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management within the company has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of an Enterprise Architecture prog-am based on TOGAF 9. An Architecture Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Enterprise Architecture team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the senior partners that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns. Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required to achieve the proposed Target Architectur
  • B. The EA team should assess the readiness of the organization to undergo chang
  • C. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
  • D. You recommend that the EA team apply an interoperability analysis to evaluate any potential issues across the Solution Architectur
  • E. This should include the development of a matrix showing the interoperability retirement
  • F. Once all of the concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.
  • G. You recommend that the EA team apply the Business Transformation Readiness Assessment technique which will allow the risks associated with the transformations to be identified and mitigated for, it will also identify improvement actions to be worked into the Implementation and Migration Pla
  • H. A Business Value Assessment should be used to determine the business value and associated risks for the transformation.
  • I. You recommend that the EA team should gather information about potential solutions from the appropriate source
  • J. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architecture
  • K. A value realization process should then be established to ensure that the concerns raised are addressed.

Answer: C

NEW QUESTION 7
Chiamin Metals is a leading world-wide manufacturer for continuous casting and bottom pouring powders. In addition to mould powders, the company also produces cored wire for secondary metallurgy. Chiamin Metals offers a variety of products and uses a paper-based catalog to sponsor them. A new CIO has joint the enterprise and has set up a team of Enterprise Architects following the TOGAF 9 practice. The main challenge is now to offer to Chiamin Metals customers a centralized and reliable entry point for their request via the implementation of a global online portal. This will allow the management of new marketing activities and will enable the new Chiamin Metals' ecommerce service.
Refer to the scenario above
You are the Chief Architect and the CIO asked you to present an Architecture Vision to address the above business problem. Identify the best answer accordingly to the TOGAF 9.
Choose one of the following answers

  • A. You identify key stakeholders, their concerns, and define the key business requirements to be addressed in the architecture engagement and generate a Stakeholder Ma
  • B. You Evaluate business capabilities and execute a Business Transformation Readiness Assessmen
  • C. You apply the Business Scenarios technique to create a high-level view of the Baseline and Target Architectures also based on the stakeholder concerns, business capability requirements, scope, constraints, and principles.
  • D. As requested by the CIO you focus on the Architecture Vision documentation and apply the Business Scenarios technique to create a high-level view of the Baseline and Target Architectures also based on the stakeholder concerns, business capability requirements, scope, constraints, and principles.
  • E. You create a high-level view of the Target Architectures and then present them to the CIO.
  • F. As requested by the CIO you focus on the Architecture Vision and create a detailed view of the Baseline Architecture
  • G. This is done for Business, Data, Application and Technology domains and then presented to the CIO using the Architecture Definition Document.

Answer: A

NEW QUESTION 8
Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question Sollace Manufacturing is a major supplier in the automotive industry, headquartered In Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff. The Sollace Manufacturing Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9. At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation. The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project. One of the earliest initiatives in the Enterprise Architecture program at Sollace Manufacturing was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution. [Note: You should assume that Sollace Manufacturing has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.] Based on TOGAF 9, which of the following is the best answer?

  • A. Common-use Applications, Data is Shared, Data is Accessible, Data Security, Interoperability, Control Technical Diversity
  • B. Business Continuity, Service-orientation, Data is Accessible, Data Security, Responsive Change Management
  • C. Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data Security
  • D. Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management

Answer: C

NEW QUESTION 9
Scenario: AutoComp Corporation
AutoComp Corporation produces components for the Car industry. Driven by the global financial downturn they are looking to reduce IT costs. They believe there is a cost saving opportunity within IT but this is not quantified in terms of potential savings nor is there agreed target architecture.
Final decisions on the solutions are not yet fully agreed. They have completed their Vision Phase and first pass of the three architecture definition phases and now they want to finalize and plan their solutions. You are the Chief Architect from a consulting organization brought into review the work to date by AutoComp Corporation and to make recommendations to the CIO and the board on this.
Which of the following answers best describes how TOGAF recommends in this context?

  • A. I would determine the business value of each solution, prioritize accordingly each set of solutions, conduct detailed Risk Assessment and Mitigation, do Compliance reviews and then implement the solution
  • B. I would present my recommendations to the board for agreemen
  • C. Once this is done, I would update the architectures reflecting any changes resulting from the board discussion.
  • D. I would after confirming Enterprise Change Attributes and constraints, do a Consolidated Gap Analysis then dependencies, then group and allocate the transition
  • E. I would also assess Enterprise readiness and risks.Then I would also assess the business value of the solutions, do risk analysis with mitigation and then schedule the work products.
  • F. I would do a Consolidated Gap Analysis by considering then dependencies, then group and allocate the transition
  • G. I would then look to produce artifacts that describe the recommended projects, the risk, issues and dependencie
  • H. This would also include transition architects to move us from current architecture to the recommended target architecture
  • I. I would present my recommendations to the board for agreemen
  • J. Once this is done, I would update the architectures reflecting any changes resulting from the board discussion.
  • K. I would look at the corporate culture and attitude to change, understand the constraints such as cost and the required time horizon
  • L. I would then look at the architecture work to ensure it is complete and seek to address any gap
  • M. I would review the functional requirements and ensure there are complete interoperability requirement
  • N. I would then validate any dependencies and risk
  • O. Then formulate an implementation and migration strategy identifies major work packages and the transition architecture require
  • P. Finally, once agreement is reached with the board I will create project charters and re-factor any changes needed from the board discussion into the architecture.

Answer: D

NEW QUESTION 10
Patterns & Co. is introducing a Commercial Off-the-Shelf (COTS) Market Analytics solution in order to improve its new delivery service.
Patterns & Co. has a mature enterprise architecture capability and the CIO is the sponsor of the enterprise architecture team. The business vision and requirements for the new system are defined. It includes a detailed business process analysis. The supplier has proposed a solution but the Architecture Board identified some of the project requirements not consistent with the adopted infrastructure standards. The CIO considered the risks and approved the implementation.
The CIO has asked the EA team to execute the Phase G ensuring that the system performance KPIs are respected, the project remains within budget and security guidelines are met.
Refer to the scenario above As Lead Enterprise Architect you have to recommend a plan to implement the CIO decision. Choose the best answer according to TOGAF 9.
Choose one of the following answers

  • A. You ask the supplier to modify the web server hardware and software components so they can meet the current infrastructure standard
  • B. You advise to execute a proof of concept to anticipate any coding issu
  • C. Then, after the agreement with the development leads for supporting the development, you will provide the project plan to the project manager and develop an Architecture Contrac
  • D. A set of frequent operational reviews to monitor the solution's performance is then scheduled after the implementation is completed.
  • E. You recommend the co-existence of a second web server standard and modify the company Standards Information Base adding this new technology.You ask the project architects to create an Architecture Contract with the development team
  • F. You identify the need of a performance testing and a compliance review You agree with the business on SLA and delivery date
  • G. You identify re-usable procedures and objects.
  • H. You eliminate the non-standard web server from the solution as recommended by the Architecture Boar
  • I. You create a revised plan and Architecture Contract for the development stressing the re-use of standard technologie
  • J. You share the budget implication of this solution with a finance committee and inform the CIO of the long term cost benefits of this choic
  • K. You define periodical project management meetings to monitor compliance.
  • L. You execute a risk analysis and set deliverables and timing requirements with the development tea
  • M. You implement a detailed impact analysis of the chosen solutio
  • N. You create an Architecture Contract and ask for the CIO's approval before implementing i
  • O. You test the solution just prior to implementation and deliver the project artifacts and store after the completion of the implementation.

Answer: B

NEW QUESTION 11
Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.
The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information Systems Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing applications?
2. What non-procurement applications will need to be integrated with any new procurement applications?
3. What data will need to be shared? Refer to the Scenario
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.
Based on TOGAF 9, which of the following is the best answer?

  • A. in the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalo
  • B. In the later Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix.
  • C. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matri
  • D. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
  • E. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/Data matri
  • F. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
  • G. In the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagra
  • H. In the later iterations of Architecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.

Answer: C

NEW QUESTION 12
SureFlight Air Carrier has received approval for the acquisition of a regional carrier.
To integrate the new acquisition, a TOGAF based enterprise architecture program has been initiated. The CIO sponsors the activity supported by the Chief Architect.
In Phase A within the initial iteration the CIO wants to ensure that the architecture activities are recognized among the various stakeholders of the enterprise.
Refer to the scenario above
You are a consultant supporting the Chief Architect that should explain how to identify and engage the stakeholders at this stage of the program.
Identify the best answer accordingly to the TOGAF 9 guidelines. Choose one of the following answers

  • A. Using the business scenarios technique you would identify supporting and not supporting stakeholders.Then you would list the set of viewpoints that are addressing the stakeholder concerns andshare these with them.
  • B. You first priority is to communicate with the regional carrier stakeholders developing a CommunicationsPlan to share main features and discuss opportunities with them.
  • C. You conduct a pilot proof of concept during Phase A to demonstrate the technical feasibility to the stakeholders explaining the approach available from your preferred suppliers.
  • D. You identify all the main stakeholders on both the acquired carrier and the rest of the enterpris
  • E. Using a stakeholder map, you classify and record their power in relation to this activit
  • F. You then focus on implementing the relevant viewpoints that can address the concerns of every main stakeholder identified in the stakeholders map.

Answer: D

NEW QUESTION 13
Scenario: Zephyr Enterprises
Please read this scenario prior to answering the question
Zephyr Enterprises specializes in the development of wind turbine blades for use in large- scale commercial wind energy production systems. Zephyr has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturers design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Zephyr has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
Zephyr has a mature Enterprise Architecture organization that is supported by a cross- functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise Architecture to closely follow the TOGAF 9 framework. All of Zephyrs IT architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and
deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Zephyr Enterprises Scenario You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

  • A. You create an Architecture Contract to manage and govern the implementation and migration proces
  • B. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contrac
  • C. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization.You recommend that if a deviation from the contract is detected, the Manufacturing Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local need
  • D. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
  • E. You create an Architecture Contract to manage and govern the implementation and migration proces
  • F. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contrac
  • G. For internal envelopment projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is detected, the Manufacturing Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • H. You create an Architecture Contract to manage and govern the implementation and migration proces
  • I. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contrac
  • J. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization.You ensure that the Manufacturing Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • K. You create an Architecture Contract to govern the implementation and migration process at each sit
  • L. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contrac
  • M. You ensure that the contract addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management.You then schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definitio
  • N. Based on the results, you ensure that the Manufacturing Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.

Answer: C

NEW QUESTION 14
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements
Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

  • A. The team should hold a series of interviews at each of the manufacturing plants using the business scenario techniqu
  • B. This will then enable them to identify and document the characteristics of the architecture from the business requirements.
  • C. The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier lis
  • D. Based on the findings from the research, the team should define a preliminary target Architecture Visio
  • E. The team should then use that model to build consensus among the key stakeholders.
  • F. The team should create Baseline and Target Architectures for each of the manufacturing plant
  • G. A gap analysis between the architectures will then validate the approach, and determine the Transition Architecture needed to achieve the target state.
  • H. The team should conduct a pilot project that will enable vendors on the short list to demonstrate potential solutions that will access the concerns of the stakeholder
  • I. Based on the findings of that pilot project, a complete set of requirements can be developed that will arrive the evolution of the architecture.

Answer: A

NEW QUESTION 15
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and
has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario:
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project.
One of the earliest initiatives in the Enterprise Architecture program at Rollins was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
[Note: You should assume that Rollins has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
Based on TOGAF 9, which of the following is the best answer?

  • A. Common-use Applications, Data is Shared, Data is Accessible, Data is Secure, Interoperability, Control Technical Diversity.
  • B. Business Continuity, Service-orientation, Data is Accessible, Data is Secure, Responsive Change Management.
  • C. Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data is Secure.
  • D. Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management.

Answer: C

NEW QUESTION 16
Scenario: Summer Seeds BV
Please read this scenario prior to answering the question Summer Seeds BV is an international agricultural company exporting bulbs, flowers and seeds worldwide. It is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities. To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes. Summer Seed's international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds. The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested information about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs. TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise Architecture practice.
Refer to the Summer Seeds BV Scenario You have been appointed as the Lead Consultant. You have been asked to recommend an approach that would enable the
development of an architecture that addresses the needs of all these parties. Based on TOGAF 9, which of the following is the best answer?

  • A. Depending on the nature of the architecture, a set of models should be created that can be used to ensure that the system will be compliant with the local regulation
  • B. Stakeholders should be able to view the models to see that their concerns have been properly addressed.
  • C. Each architecture activity should be developed using a consistent modeling approach that is uniform across all architecture project
  • D. Each architecture should be defined based on this fixed set of models so that all concerned parties can examine the models to ensure that their issues and concerns have been addressed,
  • E. A stakeholder map should be developed that allows the architects to define groups of stakeholders sharing common concern
  • F. A set of views should then be defined that addresses the concerns for each group-Architecture models can then be created for each view to address the stakeholders' concerns.
  • G. For those groups that have sufficient power and level of interest, a special report should be created that summarizes the key features of the architecture with respect to the particular locatio
  • H. Each of these reports should reflect the stakeholders' requirements.

Answer: C