Certleader offers free demo for OG0-091 exam. "TOGAF 9 Part 1", also known as OG0-091 exam, is a The-Open-Group Certification. This set of posts, Passing the The-Open-Group OG0-091 exam, will help you answer those questions. The OG0-091 Questions & Answers covers all the knowledge points of the real exam. 100% real The-Open-Group OG0-091 exams and revised by experts!

Check OG0-091 free dumps before getting the full version:

NEW QUESTION 1
Which of the following best describes the need for the ADM process to be governed?

  • A. To build a top-down, all inclusive architecture description
  • B. To enable development of reference architectures
  • C. To enable the architecture domains to be integrated
  • D. To ensure that the method is being applied correctly

Answer: D

NEW QUESTION 2
Which one of the following does TOGAF Part VII recommend in order to implement an Enterprise Architecture Capability?

  • A. Develop an Architecture Roadmap
  • B. Populate the Architecture Repository
  • C. Populate the Enterprise Continuum
  • D. Use the Architecture Development Method
  • E. Use the Implementation Governance Phase

Answer: D

NEW QUESTION 3
Which ADM phase establishes the connection between the architecture organization and the implementation organization through the Architecture Contract?

  • A. Phase E
  • B. Phase F
  • C. Phase G
  • D. Phase H
  • E. Requirements Management

Answer: C

NEW QUESTION 4
Which of the following is a re-usable artifact that is used to create architecture models addressing stakeholder concerns?

  • A. Catalog
  • B. Matrix
  • C. Diagram
  • D. View
  • E. Viewpoint

Answer: E

NEW QUESTION 5
Complete the sentence. A gap analysis will enable the architect to do all of the following except .

  • A. identify building blocks that have been inadvertently omitted
  • B. identify building blocks that have been intentionally eliminated
  • C. identify building blocks to be carried over
  • D. identify new building blocks that are needed
  • E. identify potential vendors to provide new building blocks

Answer: E

NEW QUESTION 6
Which phase of the ADM focuses on the governance and management of the Architecture Contracts that cover the overall implementation and deployment process?

  • A. Requirements Management
  • B. Phase E
  • C. Phase F
  • D. Phase G
  • E. Phase H

Answer: D

NEW QUESTION 7
What technique does TOGAF recommend that focuses on achieving business outcomes rather than just technical deliverables?

  • A. Business Transformation Readiness Assessment
  • B. Business Value Assessment Technique
  • C. Capability-Based Planning
  • D. Communications and Stakeholder Management
  • E. Quality Function Deployment

Answer: C

NEW QUESTION 8
Which of the following describes an objective of Phase G: Implementation Governance?

  • A. Finalize the Implementation and Migration Plan
  • B. Establish the recourses for architecture governance
  • C. Ensure conformance for the target architecture
  • D. Operate the governance framework
  • E. Develop the Target Technology Architecture

Answer: C

NEW QUESTION 9
Which of the following does TOGAF provide as a set of reference materials for establishing an architecture function within an organization?

  • A. Architecture Content Framework
  • B. Technical Reference Model
  • C. Integrated Information Infrastructure Reference Model
  • D. Architecture Development Method
  • E. Architecture Capability Framework

Answer: E

NEW QUESTION 10
Which of the following describes a purpose of an Architecture Compliance review?

  • A. Identifying business transformation risks for an architecture project
  • B. Identifying errors in the project architecture
  • C. Identifying relationships between management frameworks
  • D. Identifying stakeholders and their concerns

Answer: B

NEW QUESTION 11
According to TOGAF, Which of the following best describes the purpose of the Architecture Roadmap?

  • A. To ensure that architecture information is communicated to the right stakeholders at the right time
  • B. To evangelize the architecture to the end user community
  • C. To govern the architecture through to implementation
  • D. To keep the Architecture Review Board informed of changes to the architecture
  • E. To show progression of change from the Baseline Architecture to the Target Architecture

Answer: E

NEW QUESTION 12
When determining the requirements for enterprise architecture work in the Preliminary Phase, Which of the following is not a business imperative that should be considered?

  • A. Business requirements
  • B. Cultural aspirations
  • C. Forecast financial requirements
  • D. Strategic Intent
  • E. Technical elegance

Answer: E

NEW QUESTION 13
Which of the following statements best describes the purpose of the Architecture Requirements Specification?

  • A. A document that triggers the start of an architecture development cycle
  • B. A qualitative view of the solution to communicate the intent of the architect
  • C. A quantitative view of the solution to measure the implementation
  • D. A record of deviations from the planned architectural approach

Answer: C

NEW QUESTION 14
TOGAF uses a version numbering convention to illustrate the evolution of the Baseline and Target Architecture Definitions. Which version number in this convention indicates a high- level outline of the architecture?

  • A. Version 1.0
  • B. Version 0.9
  • C. Version 0.5
  • D. Version 1.5
  • E. Version 0.1

Answer: E

NEW QUESTION 15
Which of the following is described by the TOGAF Architecture Content Framework as a type of artifact that shows lists of things?

  • A. Building Block
  • B. Catalog
  • C. Diagram
  • D. Matrix
  • E. Deliverable

Answer: B

NEW QUESTION 16
TOGAF uses a version numbering convention to illustrate the evolution of the Baseline and Target Architecture Definitions. Which version number in this convention indicates a formally reviewed, detailed architecture?

  • A. Version 0.1
  • B. Version 0.5
  • C. Version 0.9
  • D. Version 1.0
  • E. Version 1.5

Answer: D

NEW QUESTION 17
In which Phase of the ADM does the business scenario technique figure most prominently?

  • A. Preliminary
  • B. Architecture Vision
  • C. Business Architecture
  • D. Information Systems Architectures
  • E. Technology Architecture

Answer: B

NEW QUESTION 18
Which of the following statements does NOT correctly describe Architecture Principles?

  • A. They are most effective when they are embraced and used across the organization
  • B. They are based on enterprise principles
  • C. They are detailed policies that prescribe behaviors and requirements
  • D. Even though they may appear generic, they should be tailored to reflect an organization's culture and goals

Answer: C

NEW QUESTION 19
Which of the following best describes the TOGAF classification in Phase H for a re- architecting change?

  • A. A change driven by a requirement to derive additional value from the existing investment
  • B. A change driven by a requirement to increase investment in order to create new value for exploitation
  • C. A change driven by a requirement to reduce costs
  • D. A change driven by a requirement to reduce investment
  • E. A change driven by a requirement to re-align with the business strategy

Answer: B

NEW QUESTION 20
Complete the sentence. TOGAF describes the role of an Architecture Contract as .

  • A. an agreement between development partners and sponsors on the architecture deliverables
  • B. a plan to ensure that architecture information is communicated to the right stakeholders at the right time
  • C. a set of general rules and guidelines to support development of the enterprise architecture
  • D. a timeline showing progression from the Baseline Architecture to the Target Architecture

Answer: A

NEW QUESTION 21
Complete the sentence. As the architecture evolves, the assets in the Solutions Continuum progress towards a (n)

  • A. Common Systems Architecture
  • B. Industry Specific Architecture
  • C. Foundation Solution
  • D. Organization Specific Solution
  • E. Technology Neutral Implementation

Answer: D

NEW QUESTION 22
Which pair of the following responses best completes the sentence? Architecture building blocks , where as Solution Building blocks

  • A. are assembled; are single function components
  • B. are single function components; are groups of architecture building blocks
  • C. are reusable; are not reusable
  • D. define the architecture; provide the existing legacy system
  • E. define functionality; define the implementation of functionality

Answer: E