Want to know Passleader ITILF2011 Exam practice test features? Want to lear more about ISEB The ITIL Foundation - 2011 certification experience? Study Certified ISEB ITILF2011 answers to Most recent ITILF2011 questions at Passleader. Gat a success with an absolute guarantee to pass ISEB ITILF2011 (The ITIL Foundation - 2011) test on your first attempt.
NEW QUESTION 1
Which of the following identifies the purpose of service transition planning and support?
- A. Provide overall planning for service transitions and co-ordinate the resources they require
- B. Ensure that all service transitions are properly authorized
- C. Provide the resources to allow all infrastructure elements of a service transition to be recorded and tracked
- D. To define testing scripts to ensure service transitions are unlikely to ever fail
Answer: A
NEW QUESTION 2
Which one of the following would be the MOST useful in helping to define roles and responsibilities in an organizational structure?
- A. RACI model
- B. Incident model
- C. Continual service improvement (CSI) approach
- D. The Deming Cycle
Answer: A
NEW QUESTION 3
Which of the following would commonly be found in a contract underpinning an IT service?
1.
Financial arrangements related to the contract
2.
Description of the goods or service provided
3.
Responsibilities and dependencies for both parties
- A. 1 and 2 only
- B. 1 and 3 only
- C. 2 and 3 only
- D. All of the above
Answer: D
NEW QUESTION 4
Which reason describes why ITIL is so successful?
- A. The five ITIL volumes are concise
- B. It is not tied to any particular vendor platform
- C. It tells service providers exactly how to be successful
- D. It is designed to be used to manage projects
Answer: B
NEW QUESTION 5
Who is responsible for ensuring that the Request Fulfillment process is being performed according to the agreed and documented process?
- A. The Service Desk Manager
- B. The Service Manager
- C. The Request Fulfillment Process Manager
- D. The Request Fulfillment Process Owner
Answer: D
NEW QUESTION 6
Which of the following is NOT an objective of Continual Service Improvement?
- A. Review and analyze Service Level Achievement results
- B. Identify activities to improve the efficiency of service management processes
- C. Improve the cost effectiveness of IT services without sacrificing customer satisfaction
- D. Conduct activities to deliver and manage services at agreed levels to business users
Answer: D
NEW QUESTION 7
Which stage of the continual service improvement (CSI) approach is BEST described by the phrase 'Understand and agree on the priorities for improvement based on a deeper development of the principles defined in the vision'?
- A. Where are we now?
- B. Where do we want to be?
- C. How do we get there?
- D. Did we get there?
Answer: B
NEW QUESTION 8
What are the categories of event described in the UIL service operation book?
- A. Informational, scheduled, normal
- B. Scheduled, unscheduled, emergency
- C. Informational, warning, exception
- D. Warning, reactive, proactive
Answer: C
NEW QUESTION 9
Which is the correct combination of Service Management terms across the Lifecycle?
- A. 1A, 2B, 3C, 4D
- B. 1C, 2D, 3A, 4B
- C. 1C, 2B, 3A, 4D
- D. 1B, 2C, 3D, 4A
Answer: C
NEW QUESTION 10
Which one of the following is NOT a valid purpose or objective of problem management?
- A. To prevent problems and resultant incidents
- B. To manage problems throughout their lifecycle
- C. To restore service to a user
- D. To eliminate recurring incidents
Answer: C
NEW QUESTION 11
Which of the following activities are performed by a service desk?
1: Logging details of incidents and service requests
2: Providing first-line investigation and diagnosis
3: Restoring service
4: Implementing all standard changes
- A. All of the above
- B. 1, 2 and 3 only
- C. 2 and 4 only
- D. 3 and 4 only
Answer: B
NEW QUESTION 12
When tan a known error record tie raised?
1) At any time when it would be useful to do so
2) After a workaround has been found
- A. 2onty
- B. 1 only
- C. Neither of the above
- D. Both of the above
Answer: C
NEW QUESTION 13
Which of the following is the BEST description of a centralized service desk?
- A. The desk is co-located within or physically close to the user community it serves
- B. The desk uses technology and other support tools to give the impression that multiple desk locations are in one place
- C. The desk provides 24 hour global support
- D. There is a single desk in one location serving the whole organization
Answer: D
NEW QUESTION 14
Which one of the following is an objective of release and deployment management?
- A. To standardize methods and procedures used for efficient and prompt handling of all changes
- B. To ensure all changes to service assets and configuration items (CIs) are recorded in the configuration management system (CMS)
- C. To ensure that the overall business risk of change is optimized
- D. To define and agree release and deployment plans with customers and stakeholders
Answer: D
NEW QUESTION 15
Which of these statements about resources and capabilities is CORRECT?
- A. Resources are types of service asset and capabilities are not
- B. Resources and capabilities are both types of service asset
- C. Capabilities are types of service asset and resources are not
- D. Neither capabilities nor resources are types of service asset
Answer: B
NEW QUESTION 16
Which of the following should IT service continuity strategy be based on?
1: Design of the service metrics
2: Business continuity strategy
3: Business impact analysis (BIA)
4: Risk assessment
- A. 1, 2 and 4 only
- B. 1, 2 and 3 only
- C. 2, 3 and 4 only
- D. 1, 3 and 4 only
Answer: C
NEW QUESTION 17
How is the Service Catalogue used to add value to the service provider organization?
- A. Providing a central source of information on the IT services delivered
- B. Showing the business impact of a change
- C. Displaying the relationships between configuration items
- D. To predict the root cause of issues in the IT infrastructure
Answer: A
NEW QUESTION 18
The BEST processes to automate are those that are:
- A. Carried out by Service Operations
- B. Carried out by lots of people
- C. Critical to the success of the business mission
- D. Simple and well understood
Answer: D
NEW QUESTION 19
Which of the following are managed by facilities management?
1: Hardware within a data centre or computer room
2: Applications
3: Power and cooling equipment
4: Recovery sites
- A. 1, 2 and 3 only
- B. All of the above
- C. 1, 3 and 4 only
- D. 1 and 3 only
Answer: C
NEW QUESTION 20
Which statement about the service portfolio is TRUE?
- A. The service portfolio includes ail services except those managed by third parties
- B. It is an integral part of the service catalogue
- C. It allows the organization unlimited resources when planning for new service deployments
- D. It represents all resources presently engaged or being released in various stages of the service lifecycle
Answer: D
Explanation:
Reference:.http://docs.livetime.com/LiveTime61/ServiceManager/service_portfolio_management.htm.(Second para)
NEW QUESTION 21
Which of the following is the best definition of IT service management?
- A. An internal service provider that is embedded within a business unit
- B. A complete set of all the documentation required to deliver world class services to customers
- C. Technical implementation of supporting IT infrastructure components
- D. The implementation and management of quality IT services that meet business needs
Answer: D
NEW QUESTION 22
The multi-level SLA' is a three-layer structure. Which one of the following layers is NOT part of this type of SLA?
- A. Customer level
- B. Service level
- C. Corporate level
- D. Configuration level
Answer: D
NEW QUESTION 23
Which one of the following is NOT a responsibility of the service transaction stage of the service lifecycle?
- A. To ensure that a service managed and operated accordance with constraints specified during design
- B. To design and develop capabilities for service management
- C. To provide good-quality knowledge and information about services
- D. To plan the resources required to manage a release
Answer: B
NEW QUESTION 24
Which of the following is a responsibility of Supplier Management?
- A. Development, negotiation and agreement of contract
- B. Development, negotiation and agreement of Organizational Level Agreements
- C. Development, negotiation and agreement of Service Level Agreement
- D. Development, negotiation and agreement of Service Portfolio
Answer: A
NEW QUESTION 25
Customer perceptions and business outcomes help to define what?
- A. The value of a service
- B. Governance
- C. Total cost of ownership (TCO)
- D. Key performance indicators (KPIs)
Answer: A
NEW QUESTION 26
The BEST description of the guidance provided by Service Design is?
- A. The design and development of new services
- B. The design and development of service improvements
- C. The design and development of services and service management processes
- D. The day-to-day operation and support of services
Answer: C
NEW QUESTION 27
Which is the BEST definition of a Configuration Item (CI)?
- A. An item of hardware or software registered in the asset database
- B. A collection of information used to describe a hardware or software item
- C. An asset, service component or other item that is, or will be, under the control of Configuration Management
- D. Information recorded by the Service Desk when an Incident is reported
Answer: C
100% Valid and Newest Version ITILF2011 Questions & Answers shared by Certshared, Get Full Dumps HERE: https://www.certshared.com/exam/ITILF2011/ (New 424 Q&As)